PROJECT OVERVIEW.
Potential for Extended Lengths +300m
This bore had the potential to extend beyond 300m by using our intercept bore methodology.
In competent ground conditions, eg shale, siltstone and sandstone in the Western Sydney basin, laser guided – vacuum spoil removal microtunnelling is very efficient.
Pipes and Grout
GRP Jacking Pipe was sliplined into this bore and grouted as per design. Most of the time – with a small bore annulus of < 25mm, grout is not necessary.